Distributed generation connection process

Information on each stage of the distributed generation connection process, including who is responsible, typical timeframes, and what may affect your application.

Key things to know



Check for likely network constraints before you apply.
Export limits or other network constraints may affect how much electricity your system can export. Check the electricity network demand and export capacity maps for an early indication of potential limits in your area.


Your requested export limit determines the application and approval process.
Applications with higher export limits require additional assessment and approval checkpoints.


Timeframes apply to both you and Vector.
These are set by the Electricity Authority. Providing complete information and responding promptly will help keep your application moving.


Complete the commissioning requirements before exporting.
Do not begin exporting electricity to Vector’s network until you have submitted the required commissioning documents and completed any other requirements that apply to your connection.



Our distributed generation connection process

Connecting a distributed generation system (solar, battery or other generation) to Vector’s network or making changes to an existing system follows a clear five-stage process.


Stage

What the installer does

What Vector does

Discovery
Understand the proposed system and identify any network requirements before detailed design work begins.


  • Confirm the property owner’s goals and future energy needs.
  • Assess the site, including property conditions, available space and electrical setup.
  • Confirm connection details, including the Installation Control Point (ICP) and any existing generation system.
  • Design the system (select proposed generation, inverter, battery and other equipment).
  • Estimate generation and exports and understand expected generation and export requirements.
  • Check network capacity using the Export capacity map and identify any potential network constraints or potential export limits.
  • Discuss any network requirements with the customer (explain export limits, approvals and potential constraints).
  • Contact Vector if additional guidance is needed, particularly for large or complex systems.
  • Answer questions about the connection process.
  • Explain network requirements and constraints.
  • Provide early guidance for large generation system installs.

Complete application
Provide the information needed for Vector to assess the proposed connection and keep the project moving smoothly.

  • Request a DG connection via orders.vector.co.nz and pay the application fee for medium / large systems.
    Note: You must provide an application for interim and final stages if applicable for medium and large applications.
  • Collect all the details needed to submit a complete application as listed on the start of our application form.
  • Confirm receipt of the application.
  • Review the information provided.
  • Request any additional information needed.
  • Confirm when the application is ready for assessment.

Assessment and approval
Assess the application and confirm the requirements for connection.

  • Monitor application progress and respond to requests for information as soon as possible.
  • Review any conditions, charges or information requests and discuss these with the customer.
  • Complete any actions needed before the application can progress.
  • Submit additional applications where required for medium or large applications.
  • Reviews the application and checks the technical and network requirements.
  • Requests additional information if required. For medium and large applications, the assessment may also include initial, interim and final approval checkpoints to confirm the project can progress to the next stage.
  • Issues an approval or decline decision for the current application checkpoint within specified timeframes. 

  • Publishes a pipeline of all large applications (>300 kW), providing visibility of their progress through the process.
  • Notifies existing distributed generation customers and large distributed generation applicants who are materially impacted by a medium or large application within 10 working days of providing approval for interim and final applications.

Agree terms
Confirm the connection requirements and any applicable agreement before installation begins.

  • Consult with the customer on whether to proceed under regulated terms or pursue a negotiated agreement.
  • Agrees a contract with customers if a separate agreement is required.

Install & Complete
Complete the installation, final checks and documentation so the system can be safely connected and commissioned.

  • Install the system within the timeframes specified under regulated terms (18 - 24 months, depending on the size of the system) or under the contract, adhering to agreed milestones.
  • Pay the observation fee if Vector asks to inspect the system.
  • Organise (if required) a two-way meter with the customer’s chosen electricity retailer.
  • Email a Certificate of Compliance (CoC), a Record of Inspection (ROI) and photos of inverter protection and control settings within 10 days after installation, to dginfo.applications@vector.co.nz to prove the physical work matches the approved engineering design.
  • For >200 kW systems you also need to provide central protection settings.
  • For medium and large systems wait until Vector reviews the commission documentation and provides the approval to turn the system on for export.
  • If required, inspects the system and observes the testing.
  • Reviews post-installation commission documentation.
  • Provides approval to turn on medium and large distributed generation installations.


Find the process that applies to your project

Select your requested export limit below to see the application and approval process that applies to your project. Vector will assess your application based on factors including the proposed system, generation type and requested export limit.


Small

Medium

Large

Up to and including 10 kW

Most residential solar / solar+battery

View small process


More than 10 kW and less than 300 kW

Large homes, apartments, schools, farms, small commercial

View medium process


300 kW and above

Large commercial, industrial & utility-scale

View large process



Medium and large applications progress through additional, interim approval checkpoints during the assessment stage:

  • medium applications have 2 checkpoints
  • large applications have 3 checkpoints.

These don't change the overall connection process but help provide greater certainty about how the project can connect to the network and what needs to happen next.


Initial approval (medium and large applications)

Initial approval means Vector has completed an early assessment of the proposal and has enough information for the project to move to the next stage of review.

Vector will outline the connection requirements, network costs, conditions or additional information needed when applying for the final approval.

You can continue developing the project while Vector carries out further assessments. Initial approval does not mean the system is approved for connection.

Interim approval (large applications only)

Interim approval means Vector’s detailed assessment indicates that the project can continue progressing towards connection, subject to any remaining requirements or conditions.

Vector will outline any connection requirements, network costs, conditions or additional information when applying for the final approval.

You can continue developing the project while Vector carries out further assessments. Interim approval does not mean the system is approved for connection.

Final approval

Final approval means the project has completed the assessment process and can proceed to installation, subject to any applicable conditions.

Vector will confirm any final connection requirements, conditions and remaining steps needed before the system can connect to and operate on the network.



Timeframes

Timeframes vary depending on the size and complexity of your project, with smaller systems often progressing more quickly than larger connections.

Timeframes are set by the Electricity Authority and apply to both you and Vector. Providing complete information and responding promptly will help keep your application moving.

The stages below happen in order, with each stage starting once the previous one is complete. Timeframes are shown in working days (WD).


Pathway

Validate application​

Approval​ initial stage​

Apply for​ interim stage​

Approve interim stage​

Apply for​ final stage​

Approve​ final stage​

Intent to​ negotiate terms​

Negotiate terms​


Vector

Vector

Customer

Vector

Customer

Vector

Customer

Vector

Small ​

≤ 10 kW​

2 wd​

N/A

N/A

N/A

N/A

10 wd

10 wd

30 wd

Medium

>10 kW –​ <300 kW​

5 wd

40 wd

N/A

N/A

12 months

45 wd

30 wd

30 wd

Large

300 kW – <1 MW​

5 wd

40 wd

12 months

45 wd

90 wd

20 wd

30 wd

30 wd

Large

1 MW – <3 MW​

5 wd

40 wd

12 months

60 wd

90 wd

30 wd

30 wd

30 wd

Large

≥ 3 MW​

5 wd

40 wd

12 months

80 wd

90 wd

40 wd

30 wd

30 wd


Once your application has received final approval, small systems must be connected and operating within 18 months, and medium and large systems within two years, unless we’ve agreed a different timeframe with you. This is a regulated requirement. You’ll also need to meet any other deadlines set out in your contract.



Keeping your application on track

We aim to make the connection process as straightforward and transparent as possible. Assessment timeframes start once we’ve received a complete application and any applicable fees.


Help keep your application moving

Your application is more likely to stay on track when the following actions are completed promptly:

  • Providing additional information when requested.
  • Completing any approval conditions.
  • Required agreements are accepted.
  • Testing or compliance documents are submitted.


Pausing the assessment timeframe

The assessment timeframe is paused for medium and large applications if we're waiting for:

  • information or clarification from you or your installer.
  • required network upgrades to accommodate your proposed export amount.
  • the site to be livened and issued with an ICP number.

The assessment timeframe will resume once the relevant requirement has been completed.

You can also request a pause if circumstances outside your control are causing delays.


Is more time needed?


Sometimes additional time is needed to gather information, complete required actions, or finalise an assessment.

In these situations, either you or Vector can request an extension. Any extension must be agreed by both parties.



Need help?


If you're unsure which approval pathway applies to your project, have questions about network constraints, or need help with next steps, contact Vector's distributed generation team before progressing your application. Getting in touch early can help avoid delays later in the process.

Email us