Distributed generation connection process
Information on each stage of the distributed generation connection process, including who is responsible, typical timeframes, and what may affect your application.
Key things to know
Check for likely network constraints before you apply. | |
Your requested export limit determines the application and approval process. | |
Timeframes apply to both you and Vector. | |
Complete the commissioning requirements before exporting. |
Our distributed generation connection process
Connecting a distributed generation system (solar, battery or other generation) to Vector’s network or making changes to an existing system follows a clear five-stage process.
Stage | What the installer does | What Vector does |
|---|---|---|
Discovery |
|
|
Complete application |
|
|
Assessment and approval |
|
|
Agree terms |
|
|
Install & Complete |
|
|
Find the process that applies to your project
Select your requested export limit below to see the application and approval process that applies to your project. Vector will assess your application based on factors including the proposed system, generation type and requested export limit.
Small | Medium | Large |
|---|---|---|
Up to and including 10 kW Most residential solar / solar+battery View small process | More than 10 kW and less than 300 kW Large homes, apartments, schools, farms, small commercial View medium process | 300 kW and above Large commercial, industrial & utility-scale View large process |
Medium and large applications progress through additional, interim approval checkpoints during the assessment stage:
- medium applications have 2 checkpoints
- large applications have 3 checkpoints.
These don't change the overall connection process but help provide greater certainty about how the project can connect to the network and what needs to happen next.
Initial approval (medium and large applications) | Initial approval means Vector has completed an early assessment of the proposal and has enough information for the project to move to the next stage of review. Vector will outline the connection requirements, network costs, conditions or additional information needed when applying for the final approval. You can continue developing the project while Vector carries out further assessments. Initial approval does not mean the system is approved for connection. |
|---|---|
Interim approval (large applications only) | Interim approval means Vector’s detailed assessment indicates that the project can continue progressing towards connection, subject to any remaining requirements or conditions. Vector will outline any connection requirements, network costs, conditions or additional information when applying for the final approval. You can continue developing the project while Vector carries out further assessments. Interim approval does not mean the system is approved for connection. |
Final approval | Final approval means the project has completed the assessment process and can proceed to installation, subject to any applicable conditions. Vector will confirm any final connection requirements, conditions and remaining steps needed before the system can connect to and operate on the network. |
Timeframes
Timeframes vary depending on the size and complexity of your project, with smaller systems often progressing more quickly than larger connections.
Timeframes are set by the Electricity Authority and apply to both you and Vector. Providing complete information and responding promptly will help keep your application moving.
The stages below happen in order, with each stage starting once the previous one is complete. Timeframes are shown in working days (WD).
Pathway | Validate application | Approval initial stage | Apply for interim stage | Approve interim stage | Apply for final stage | Approve final stage | Intent to negotiate terms | Negotiate terms |
|---|---|---|---|---|---|---|---|---|
Vector | Vector | Customer | Vector | Customer | Vector | Customer | Vector | |
Small ≤ 10 kW | 2 wd | N/A | N/A | N/A | N/A | 10 wd | 10 wd | 30 wd |
Medium >10 kW – <300 kW | 5 wd | 40 wd | N/A | N/A | 12 months | 45 wd | 30 wd | 30 wd |
Large 300 kW – <1 MW | 5 wd | 40 wd | 12 months | 45 wd | 90 wd | 20 wd | 30 wd | 30 wd |
Large 1 MW – <3 MW | 5 wd | 40 wd | 12 months | 60 wd | 90 wd | 30 wd | 30 wd | 30 wd |
Large ≥ 3 MW | 5 wd | 40 wd | 12 months | 80 wd | 90 wd | 40 wd | 30 wd | 30 wd |
Once your application has received final approval, small systems must be connected and operating within 18 months, and medium and large systems within two years, unless we’ve agreed a different timeframe with you. This is a regulated requirement. You’ll also need to meet any other deadlines set out in your contract.
Keeping your application on track
We aim to make the connection process as straightforward and transparent as possible. Assessment timeframes start once we’ve received a complete application and any applicable fees.
Help keep your application moving
Your application is more likely to stay on track when the following actions are completed promptly:
- Providing additional information when requested.
- Completing any approval conditions.
- Required agreements are accepted.
- Testing or compliance documents are submitted.
Pausing the assessment timeframe
The assessment timeframe is paused for medium and large applications if we're waiting for:
- information or clarification from you or your installer.
- required network upgrades to accommodate your proposed export amount.
- the site to be livened and issued with an ICP number.
The assessment timeframe will resume once the relevant requirement has been completed.
You can also request a pause if circumstances outside your control are causing delays.
Is more time needed?
Sometimes additional time is needed to gather information, complete required actions, or finalise an assessment.
In these situations, either you or Vector can request an extension. Any extension must be agreed by both parties.
Need help?
If you're unsure which approval pathway applies to your project, have questions about network constraints, or need help with next steps, contact Vector's distributed generation team before progressing your application. Getting in touch early can help avoid delays later in the process.
Email usRelated distributed generation pages
Connect your solar panels, battery, wind turbine and vehicle-to-grid
Learn about distributed power generation
Technical information for distributed generation installers
Learn about our technical requirements
Managing electricity exports
Learn about exporting excess electricity back to our network
Distribution generation application pipeline
View the pipeline of large generation projects (300 kW and above)
FAQs
The information you need will depend on your system and application type. Before you start, make sure you have the relevant information and documents ready. Some technical information may need to come from your installer or equipment supplier.
Site and connection details |
|
|---|---|
Contact details |
|
Generating system details |
|
Inverter details |
|
Battery details, if applicable |
|
Supporting documents |
|
For large applications (>300 kW), Vector publishes a pipeline that provides visibility of projects progressing through the connection process. This helps applicants and existing customers understand activity across the network. Specific technical and location details of applications are not published.
Following approval, you’ll need to decide whether to proceed under the regulated terms or negotiate a separate agreement, where this option is available. If Vector doesn’t receive notice of intent to negotiate within the required timeframe, the regulated terms will apply as your connection contract.
You can discuss the decision with Vector and provide any additional information that may be relevant. If you’re still dissatisfied, you can follow Vector’s complaints process or seek external review through the Electricity Authority or Utilities Disputes, where appropriate.
You must meet the timeframes and milestones set out in the regulated terms or any separate contract. Missing these deadlines may affect your ability to connect or may require you to reapply. If you expect a delay, contact Vector as early as possible to discuss your options.
Vector aims to meet the published timeframes. If a delay occurs, we’ll keep you informed and explain any impacts on your application.
If you have concerns, you can contact your Vector representative or raise the matter through Vector’s complaints process.