Distributed generation application pipeline
The Distributed Generation (DG) pipeline shows large generation projects (300 kW and above) that are progressing through Vector's connection process.
How the pipeline can help
You can use the pipeline to:
- View large generation projects currently progressing through the connection process.
- Understand where demand for network capacity may be increasing.
- Consider potential network constraints when planning a new project.
- Support early discussions with Vector about larger or more complex connections.
- Make more informed decisions about future generation projects.
Information published through the pipeline
The pipeline includes information about large generation projects that have entered Vector’s connection process. The pipeline only shows certain information about projects, and that information is determined in accordance with regulatory requirements and our management policy.
Current pipeline
Our application pipeline is coming soon
We’re getting our Distributed Generation application pipeline ready to share with you. It’ll be available here from 1 December 2026. Check back then to explore large generation projects and see where they are in the connection process.
Related distributed generation information
Connect your solar panels, battery, wind turbine and vehicle-to-grid
Learn about distributed power generation
Distributed generation connection process
Learn about our process and typical timeframes
Technical information for distributed generation installers
Learn about our technical requirements
Managing electricity exports
Learn about exporting excess electricity to our network
FAQs
No. Projects may be at different stages of the connection process. Being included in the pipeline does not mean a project has been approved or will proceed to connection. And only projects over 300 kW are shown on the pipeline.
Potentially. Large generation projects can affect the amount of network capacity available in a particular area. Reviewing the pipeline alongside our export maps can help you understand planned generation activity before submitting an application. The impact is indicative only until a project is approved and installed.
Priority projects can change as projects:
- Progress through the connection process.
- Are withdrawn.
- Expire or no longer meet required milestones.
- Lose eligibility to retain their place in the queue.
Priority positions are managed to ensure projects are progressed fairly and that available network capacity is used efficiently.