Technical information for distributed generation installers
We're here to help installers design, apply for and connect distributed generation systems safely and efficiently.
Whether you're installing solar, batteries, wind generation or vehicle-to-grid (V2G) technology, this information will help you understand the technical requirements, approved equipment, connection standards and supporting guidance needed to keep your project moving smoothly.
Key things to know
Technical requirements. | |
Approved equipment and settings. | |
Network capacity and export limits. | |
Connection approval. | |
Testing and commissioning. | |
Documentation and permission to operate. | |
Qualifications and competency Distributed generation systems must be designed and installed by appropriately qualified professionals. Electrical work must be carried out by a registered electrical worker, and installers should hold the relevant industry accreditation, registration and manufacturer training for the equipment being installed. |
How Vector supports installers
We aim to make the connection process as straightforward as possible by:
- Providing information about network capacity and export constraints.
- Publishing technical requirements and providing approved equipment lists.
- Assessing applications and providing feedback.
- Supporting early engagement for larger or more complex projects.
- Clarifying technical requirements where needed.
Installer checklist
Use the installer checklist to confirm you’ve completed the required design, application, installation and commissioning checks for your project.
All applications | Additional - over 10 kW | |
|---|---|---|
Before you apply |
|
|
After approval to installer |
Note: Initial or interim approval may include conditions: Final approval follows once all conditions are met. |
|
After install / before export |
Within 10 working days:
|
|
Technical requirements
Distributed generation systems connected to Vector's network must meet relevant industry standards and Vector's technical requirements.
Use the requirements below when designing, installing, testing and commissioning a distributed generation system.
Core standards and Vector requirements
- AS/NZS 3000 - Electrical Installations (Wiring Rules).
- AS/NZS 4777.1:2024 - Grid connection of energy systems via inverters - Part 1: Installation requirements.
- AS/NZS 4777.2:2020 - Grid connection of energy systems via inverters - Part 2: Inverter requirements.
- Vector's technical requirements for distributed generation connections less than 30 kW installed capacity - ESP009.
- Vector's technical requirements for distributed generation connections greater than 30 kW installed capacity - ESP005.
- Our electricity network connection standard.
Always check the latest published version of the relevant standards and Vector requirements before designing or installing a system.
Inverter, protection and safety requirements
When designing, installing and commissioning a distributed generation system:
- Check whether the inverter is an approved inverter.
- If it is not on the approved list, provide Vector with an inverter datasheet and Certificate of Suitability confirming compliance with AS/NZS 4777.2:2020.
- Configure the inverter to the AS/NZS 4777.2:2020 Australia A settings before commissioning, unless Vector has confirmed different settings for the connection.
- Enable required grid-support functions, including Volt-Watt and Volt-Var, and correctly apply anti-islanding, voltage and frequency protection settings.
- Ensure the system automatically disconnects during a power outage and cannot energise the network when the network has been de-energised.
- Meet all applicable isolation, earthing, labelling and signage requirements.
- Ensure battery energy storage systems comply with AS/NZS 5139 where applicable.
- Check Vector’s latest technical requirements before installation. Larger, complex or non-standard systems may have additional equipment, protection, settings, testing or documentation requirements.
Designing for export limits
Discuss export limits with customers early. On-site consumption, battery storage and dynamic exports can affect system performance, and the export limit that Vector approves may be lower than the system’s nameplate capacity.
Nameplate capacity (also known as rated capacity, nominal capacity or installed capacity), is the maximum installed generating capacity that a distributed generation system is capable of. It is based on the rated capacity of the generating equipment, such as solar panels, wind turbines, and inverters. Where applicable, it may also include the maximum discharge capacity of a battery energy storage system.
This represents the system's theoretical maximum generation capacity under standard or ideal operating conditions. It doesn’t necessarily reflect the amount of power that can be generated or exported to the electricity network.
Export limit is the maximum amount of power a distributed generation system is permitted to export to the electricity network at any given time. Export limits are typically enforced through inverter settings, control systems, or protection schemes.
The export limit is determined by Vector based on network capacity and operational requirements and may be significantly lower than the system's nameplate rating.
Understanding this difference between nameplate capacity and export limit is crucial as it may impact system design strategies. Design the system to:
- Consider potential export limits shown on the export capacity map.
- Consider that the approved export limit may be lower than the system’s generating capacity or the amount requested.
- Support the customer’s objectives.
- Align with available network capacity.
- Meet Vector’s current technical requirements.
Dynamic exports
If the proposed connection is eligible for dynamic exports (currently available for small connections only), the inverter must:
- Comply with AS/NZS 4777.2:2020.
- Be CSIP-capable.
- Have CSIP communication enabled from the date of installation and maintain a continuous internet connection.
The customer must also agree that Vector can connect the inverter to Vector's export management system.
Fallback behaviour: if communication is lost, the inverter automatically reverts to a fixed 2.5 kW export limit until the connection is restored.
Commissioning documentation
Provide the required commissioning documentation to Vector within 10 working days. For all system sizes, provide:
- A Certificate of Compliance (CoC).
- A Record of Inspection (RoI).
- A clear photo of the inverter nameplate (must include the serial number).
- A clear photo or csv / pdf export of inverter protection setting.
- A clear photo or csv / pdf export of Volt-Var / Volt-Watt control settings (if applicable).
Medium and large systems
Additional requirements may apply depending on the size and design of the system. These can include:
- Additional protection requirements.
- A central protection relay for systems over 200 kW.
- Other testing, commissioning or technical information required by Vector.
Check Vector’s current technical requirements to see what applies to your system.
Need help?
If you have a technical question about a specific design or installation, contact Vector’s distributed generation technical team before submitting the application. Early clarification helps avoid delays later in the process.
Email usRelated distributed generation information
Connect your solar panels, battery, wind turbine and vehicle-to-grid
Learn about distributed power generation
Distributed generation connection process
Learn about our process and typical timeframes
Managing electricity exports
Learn about exporting excess electricity back to our network
Distributed generation application pipeline
View the pipeline of large generation projects (300 kW and above)
FAQs
Yes. Battery energy storage systems must also comply with AS/NZS 5139, where applicable.
However, the overall system must still meet AS/NZS 4777 and Vector’s technical requirements.
Export must be balanced in accordance with AS/NZS 4777. Systems that don’t meet the applicable phase-balance requirements may require additional protection or may not be able to be connected as proposed.
They are published in Vector’s technical requirements documents. Always check that you’re using the latest published version before designing, installing or commissioning a system.
Useful Links
- Electricity Industry Participation Code 2010: Part 6 - Connection of distributed generation
- Approved inverters (Clean Energy Council)
- Approved batteries (Clean Energy Council)
- Our technical requirements for distributed generation connections greater than 30 kW installed capacity - ESP005
- Our technical requirements for distributed generation connections less than 30 kW installed capacity - ESP009
- Our electricity network connection standard
- Our network demand and export capacity maps
- Our network capacity map
- Our congestion management policy
- Customer portal FAQs