Complex connection supply point
Once we have assessed your new connection application, if the connection process is described as a ‘complex connection supply point’, the job requires a customer works agreement and easements, if applicable. These jobs generally have longer timeframes as they are more complex.
If you need both gas and electricity connections, please request them separately.
Apply for a complex connection
Please fill out the below application to start the connection process
Start applicationExplore this page:
Pricing
When you add a new connection or upgrade an existing connection on the electricity network, you will pay:
- The cost of the connection at the point of supply (connection fee);
- Contribution towards costs of increasing capacity in the shared network (development contribution); and
- The cost we incur when preparing a detailed quote (assessment fee).
Connection fee | Development contribution | Assessment fee | Total |
|---|---|---|---|
Pricing effective from 1 April 2026 (incl. GST) | |||
Priced per job | See table below | Priced per job | Priced per job |
Development contribution
Network Tier | Connection type | Amount ($ per icp) | Rate ($ per installed kVA) |
|---|---|---|---|
Pricing effective from 1 April 2026 (Incl. GST) | |||
Low voltage mains | Residential 0 - 14kVA Residential 15 - 69kVA SME 14 - 28kVA SME 29 - 42kVA SME 43 - 69kVA Other low voltage mains | $3,193 $5,339 $3,703 $7,478 $15,274 | $264.50 |
Distribution substation | Priced per job | ||
High voltage feeder | Priced per job | ||
Zone substation | Priced per job | ||
Sub-transmission line | Priced per job | ||
Civil work and traffic management
New electricity connections may require civil work and/or traffic management. You have the option to organise this yourself, using appropriately qualified providers who can meet the relevant standards and requirements. Alternatively, we can arrange it for you through our service providers. We are happy to talk through the options with you during the assessment of your connection request.
For some complex works that involve critical network infrastructure, we may need to use our specialist contractors to complete parts of the civil work. This ensures the safety and integrity of the network. Where this applies, you cannot, unfortunately, organise those specific aspects independently. If this is the case, we will let you know during the connection process.
If you choose to organise your own civil works, Vector will need to carry out quality assurance inspections to ensure those works meet the necessary safety and network requirements. A fee applies for this inspection process, which we’ll discuss and confirm with you as part of your connection costs.
Refunds
Sometimes we complete work faster than anticipated, for example, less traffic management days are needed. This may result in a partial refund of the contribution that you paid. Ordinarily we’ll process any refunds after the completion of the work when we know what work was (and was not) required.
Network capacity charges:
Vector charges capacity costs to connection applicants. The rates in the table below are for information purposes only and reflect the cost of capacity determined in accordance with new regulations set by the Electricity Authority, using the best information available at the time of preparation.
For the period 1 April 2026 to 31 March 2027, we will be charging for capacity costs on the basis set out in the table above (development contribution), which is broadly in line with our historical development contribution approach.
We are required to charge capacity costs from 1 April 2027 in accordance with new regulations set by the Electricity Authority. Between 1 April 2026 to 31 March 2027, we will test the rates and the information used to prepare those rates in the table below and on completion of that testing make any necessary adjustments. Therefore, the actual rates that will be used for charging capacity from 1 April 2027 will be published in due course.
For the avoidance of doubt the rates in the table below are for information purposes only and the rates we will use for capacity charging are yet to be determined. The nominal capacity increment is the estimated added capacity used to derive the posted capacity rates.
Network Tier | Posted capacity rates ($ incl. GST per diversified kVA) For information purposes | Nominal incremental capacity (installed kVA) | ||||
|---|---|---|---|---|---|---|
1st April 2026 | 1st April 2027 | 1st April 2028 | 1st April 2029 | 1st April 2030 | ||
Low voltage mains | - | - | - | - | - | - |
Distribution substation | $176.67 | $180.62 | $185.12 | $189.95 | $195.02 | 687,891 |
High voltage feeder | $715.89 | $731.92 | $750.15 | $769.72 | $790.28 | 321,650 |
Zone substation | $330.38 | $337.78 | $346.19 | $355.22 | $364.71 | 1,427,250 |
Sub-transmission line | $370.74 | $379.05 | $388.49 | $398.62 | $409.27 | 625,250 |
Active pioneer schemes
A pioneer scheme is a refund mechanism that electricity distributors are required to set up from 1 April 2026 so that the customer who initially funds a qualifying network extension can be reimbursed by later customers who connect to and use that same extension.
This means that initial connections may receive refunds if others connect later and subsequent connections may be charged to contribute to earlier shared infrastructure.
If a pioneer scheme is relevant to your connection, we will explain this clearly as part of your quote.
The table below shows details of the current active pioneer schemes:
Pioneer reference | Location | Start date | End Date | Opening value ($) |
|---|---|---|---|---|
There is currently no active Pioneer scheme in place | ||||
Our process
Process and timelines
The process, costs, and timeframes may vary depending on a number of factors, including:
- The type of network connection supply point required - which depends on the available capacity
- The number of connections you require and whether the connections are temporary or permanent
- The available capacity as well as fuse and phase requirements (your electrician will provide these details)
- Whether an easement is required to allow gas and electricity equipment owned by Vector to be installed and to remain on private property. An easement provides us with ongoing access and maintenance rights in respect of that equipment.
- The conditions of the work site and the complexity of the job
- Vector’s current work volumes
- When traffic management services are next available (as these are managed by third parties) and the availability of equipment required
- Other technical, legal, regulatory and administrative factors (including resource constraints)
Our process
Initiate | Submit your application online when requesting electricity connections. You’ll usually receive an indicative quote within 10 working days |
|---|---|
Design | You'll need to pay for the design cost for the job to proceed . We'll usually advise you within 1 week after payment when the design will be completed. |
Contract and payment | Once we’ve received design approval, we'll aim to send you a customer works agreement within 5 working days (that is valid for 45 days). We'll then contact you to schedule the work once the agreement has been signed and payment received . |
Build and variations | Work will usually begin approximately 6 weeks after receipt of payment |
Completion | When you are ready to liven your connection click here. For subdivisions we will issue a completion certificate once all Vector equipment is tested and livened and we have received and approved a land transfer plan (if required by the easements) |
Information required before you apply
- Site plan, lot layouts, location of other services including trench profiles
- Required number of phases and amp size
- Resource consent information for subdivisions and power pole relocations
FAQs
Please visit orders.vector.co.nz to request the electricity connection and call 0800 22 22 60 to request the gas connection. As these are different connections with different processes, you will need to request these separately.
Every project needs a site-specific design for its electricity and gas supply. If you contact us early in your project, we can assist you with more accurate design and pricing of your electricity and/or gas supply
Detailed design of a gas or electricity connection is carried out by our service providers which incurs a design fee. Please note that depending on the job, other design related costs may be incurred such as pole calculation, capacity logging, or pilot hole costs. Completing these activities in the design stage provides more cost certainty for the project and reduces potential variations.
A contribution applies to all customer-initiated projects. Vector’s policy for determining capital contributions can be found here.
The work will be carried out by one of our approved service providers. These service providers have been carefully selected by Vector and work with us to provide all installation and maintenance services on our network.
Vector usually owns the network equipment up to the point of supply. We are responsible for the ongoing ownership and maintenance of our own assets. Equipment beyond the point of supply is usually installed, owned and maintained by the customer.
Electricity and gas easements are important because they benefit both Vector and landowners by:
- Protecting a landowner’s safety by formally recording the location of the gas and/or electricity reticulation equipment on their property title.
- Providing us with legal rights to access your property so that we can operate, maintain or replace our equipment.
Easements are required over installed Vector owned gas and electricity equipment to allow those assets to remain on private property and to provide us with ongoing access rights.
Vector owned equipment means equipment installed by us as part of our work supplying customers with electricity or gas. This can include pits, poles, lines, cables, fuses and transformers, gas pipes, gas measurement systems, distribution systems and fittings, and other associated equipment.
Private property means real property that is privately owned and includes privately and jointly owned access roads in subdivisions, Council local purpose reserve or recreation land and Crown land.
Equipment installed on private property before 1 January 1993
For electricity and gas equipment installed on private property prior to 1 January 1993, we have existing use rights (which is a statutory right contained in the Electricity Act 1992) and will not usually require an easement unless we need to install new equipment or relocate existing equipment.
If new equipment is to be installed, we will require an easement over all new equipment together with any existing equipment as it may no longer be protected under the pre-existing statutory use rights.
We will let you know when an easement is required, and whether this is for new or existing electricity equipment. Where an easement is required, the obligation to grant an easement will form part of your contract with us to undertake the works.
We have standard easement terms which grant us necessary rights to access your property to inspect, operate and maintain our equipment. These must remain standard and unamended, for all properties throughout Auckland, so that our contractors and maintenance team can rely on them.
To register an easement, following installation of equipment, either we or the customer will organise a survey plan (depending on our contract together) which shows the area that will be granted to Vector for our easement. A legal document called the ‘easement instrument’ is then prepared by our legal team and sent to your solicitor. The registration of the easement on your property title will be processed by us together with your lawyer.
Substations consist of high voltage switchgear, transformers and low voltage fusing and associated housing. Substation requirements are set out in our standards which are available on request. Details of specific sizes, safety requirements, and other factors will be provided by your Vector contact.
- Outdoor substations require you to allocate a suitable area of land on which to install a self-contained substation.
- Indoor substations are often needed in high density areas (ie. Auckland’s CBD) and require you to construct and maintain a suitable room.
You will need to arrange for a registered electrician to specify the type of connection required for your site. Refer to “What information do I need to supply?" above for a breakdown of the information we need from you and your electrician.
There are many aspects that affect the price you pay for the installation, some of these include:
- Complexity of the project (i.e. CBD location; existing services etc.)
- Distance from our existing network
- Type and size of infrastructure required
- Amount of civil works and/or trenching
- Reticulation distances
- Compliance costs (i.e. consents, road opening notices, traffic management)
- Land base – some areas in Auckland have large areas of volcanic rock which can increase installation costs (if you are able to provide trenches in your development then costs can be kept to a minimum).
If you hit a fibre cable, please call us immediately on 0800 826 436 (select option 1, then select option 2 for Vector Fibre).
Useful Links
- Electricity Authority Price Disclosure FAQ
- Capital contributions
- Electricity disclosures
- Network connection standard
- Connect together
- Accurate service records
- Working near Vector's network
- Smart metering guidelines
- NZECP 34 - New Zealand Electrical Code of Practice for Electrical Safe Distances
- Gas disclosures