Complex connection supply point

After we review your application, we will tell you if it is a complex connection. A complex connection needs a customer works agreement and may also need an easement. Because these connections involve more work, they usually take longer to complete.  

If you need both gas and electricity connections, please request them separately  here.

Apply for a complex connection

Please fill out the below application to start the connection process

Start application

Pricing

When you add a new connection or upgrade an existing connection on the electricity network, you will pay:

  • Design fee – If the connection request is identified as complex, we will provide an indicative cost. If the customer wishes to proceed to detailed design, a $3,000 + GST design fee will apply. Once the detailed design is accepted, we will provide the final project cost through a Customer Works Agreement (CWA).
  • Price comparison – Once the detailed design is complete and accepted, we will obtain pricing from the Field Service Provider (FSP) assigned to deliver the work. Where available, we can also seek pricing from alternative FSPs so you can compare prices before proceeding.
  • The cost of the lowest-cost connection design – this covers the work needed to connect your property or upgrade your existing connection, based on the lowest-cost design that meets Vector’s network standards.
  • Any customer-selected enhancements – these are optional enhancements you request above the lowest-cost design and will be shown separately in your Customer Works Agreement. For example, this could include requesting a power pole to be removed. 


Connection fee

Development contribution

Assessment fee

Total

Pricing effective from 1 April 2026 (incl. GST)

Priced per job

See table below

Priced per job

Priced per job


Development contribution


Network Tier

Connection type

Amount

($ per icp)

Rate

($ per installed kVA)

Pricing effective from 1 April 2026 (Incl. GST)

Low voltage mains


Residential 0 - 14kVA

Residential 15 - 69kVA

SME 14 - 28kVA

SME 29 - 42kVA

SME 43 - 69kVA

Other low voltage mains

$3,193

$5,339

$3,703

$7,478

$15,274







$264.50

Distribution substation


Priced per job

High voltage feeder


Priced per job

Zone substation


Priced per job

Sub-transmission line


Priced per job


Civil work and traffic management

New electricity connections may require civil work and/or traffic management. You have the option to organise this yourself, using appropriately qualified providers who can meet the relevant standards and requirements. Alternatively, we can arrange it for you through our service providers. We are happy to talk through the options with you during the assessment of your connection request. 

For some complex works that involve critical network infrastructure, we may need to use our specialist contractors to complete parts of the civil work. This ensures the safety and integrity of the network. Where this applies, you cannot, unfortunately, organise those specific aspects independently. If this is the case, we will let you know during the connection process. 

If you choose to organise your own civil works, Vector will need to carry out quality assurance inspections to ensure those works meet the necessary safety and network requirements. A fee applies for this inspection process, which we’ll discuss and confirm with you as part of your connection costs.

Design Fee – We will provide an indicative cost for the requirements based on a desktop assessment and initial checks. If you require a firm design and cost, a design fee of $3,000 + GST will apply.


Refunds

Sometimes the work may cost less than we originally quoted, for example if fewer traffic management days are needed. If this happens, we’ll refund you the difference once the work is complete.


How development contributions relate to network capacity

When you connect to the network or upgrade your connection, you use some of the network’s available capacity.

The network capacity cost is the estimated cost of providing the shared network capacity used or added to support your connection. Your development contribution is the amount you are asked to contribute towards this cost and may be less than the full network capacity cost.

Our approach is that customers creating growth on the network should contribute towards the investment needed to support that growth. How these costs are shared is subject to electricity industry regulation.

For more information about development contributions, network capacity costs and how these are changing, see our FAQs below.

 The nominal capacity increment is the estimated increase in network capacity used to calculate the indicative capacity rates.


Network Tier

Posted capacity rates ($ excl. GST per diversified kVA)

For information purposes

Nominal incremental capacity (installed kVA)


1st April 2026

1st April 2027

1st April 2028

1st April 2029

1st April 2030


Low voltage mains

-

-

-

-

-

-

Distribution substation

$176.67

$180.62

$185.12

$189.95

$195.02

687,891

High voltage feeder

$715.89

$731.92

$750.15

$769.72

$790.28

321,650

Zone substation

$330.38

$337.78

$346.19

$355.22

$364.71

1,427,250

Sub-transmission line

$370.74

$379.05

$388.49

$398.62

$409.27

625,250


Pioneer schemes

A pioneer scheme helps make sure the cost of new electricity infrastructure is shared fairly.

If you’re the first customer to pay for a qualifying network extension, you may receive a refund if other customers later connect to and use that same infrastructure in the future.

Likewise, if you connect later and benefit from infrastructure someone else helped fund, you may need to contribute to these costs.

If a pioneer scheme is relevant to your connection, we will explain this clearly as part of your quote.

The table below shows the pioneer schemes that are currently active:


Pioneer reference

Location

Start date

End Date

Opening value ($)

There is currently no active Pioneer scheme in place


Our process


Process and timelines

The process, costs, and timeframes may vary depending on a number of factors, including:

  • The type of network connection supply point required - which depends on the available capacity
  • The number of connections you require and whether the connections are temporary or permanent
  • The available capacity as well as fuse and phase requirements (your electrician will provide these details)
  • Whether an easement is required to allow gas and electricity equipment owned by Vector to be installed and to remain on private property. An easement provides us with ongoing access and maintenance rights in respect of that equipment. 
  • The conditions of the work site and the complexity of the job 
  • Vector’s current work volumes 
  • When traffic management services are next available (as these are managed by third parties) and the availability of equipment required 
  • Other technical, legal, regulatory and administrative factors (including resource constraints)


Our process


Initiate

Submit your application online when requesting electricity connections. You’ll usually receive an indicative quote within 10 working days

Design

You'll need to pay for the design cost for the job to proceed . We'll usually advise you within 1 week after payment when the design will be completed.

Contract and payment

Once we’ve received design approval and pricing, we'll aim to send you a customer works agreement within 5 working days (that is valid for 45 days). We'll then contact you to schedule the work once the agreement has been signed and payment received .

Build and variations

Work will usually begin approximately 6 weeks after receipt of payment

Completion

When you are ready to liven your connection click here. For subdivisions we will issue a completion certificate once all Vector equipment is tested and livened and we have received and approved a land transfer plan (if required by the easements) 


Information required before you apply

  • Site plan, lot layouts, location of other services including trench profiles
  • Required number of phases and amp size
  • Resource consent information for subdivisions and power pole relocations