Connect power generation - more than 10kw

The following information applies when you generate your own electricity on-site via a generator producing more than 10 kilowatts which is, or will be, connected to our electricity network.

We can approve your application if you provide evidence that your distributed generation complies with our technical requirements.


Your application may be delayed in processing if:

  • Your inverter does not meet our technical requirements; and/or
  • The information provided in your application was not complete
  • More information is required and/or approval from a technician is required

Once your application is approved, unless otherwise agreed, your connection will be governed by the regulated terms (Schedule 6.2) and our Congestion Policy.



Your responsibilities


Before you apply

  • Check your inverter is approved and compliant using our approved list
  • If your inverter is not on the list, please provide the Certificate of Suitability which shows compliance with ASNZS 4777.2:2015 with your application.
  • Read the following documents:

After installation provide us with

  • A Certificate of Compliance outlining the scope of the installation (including reference to compliance to AS/NZS 4777.1 and AS/NZS 3000) within 10 working days after installation
  • Payment for connection related costs
  • Inverter protection settings
  • Inverter Volt-VAr and Volt Watt control settings (if applicable)
  • Central protection settings (for >30kW only)
  • The connection schedule


Upfront application fee

We will charge an initial application fee to help cover our costs to analyse and review the information you provide. The fee varies depending on the size of your connection.

The rates outlined below align with the Electricity Authorities new amendments to distributed generation fees, which took effect from 1 November 2024.


Connection size

Application fee

>10kW and <100kW

$770*

>100kW and <1MW

$1,540*

>1MW

$7,690*

*In accordance with Schedule 6.5, under Part 6 of the Code


On-site observation and testing fee

Depending on the installation, we may conduct an inspection to ensure that we are satisfied with the installation. The fee varies depending on the size of your connection.

The rates outlined below align with the Electricity Authorities new amendments to distributed generation fees, which took effect from 1 November 2024.


Connection size

Application fee

>10kW and <100kW

$180*

>100kW

1,850*

*In accordance with Schedule 6.5, under Part 6 of the Code


Our Process


Initiate

Submit the initial application form to DGinfo.applications@vector.co.nz.
We’ll contact you to discuss your application and issue an invoice

Design and installation

Once we’ve received your payment, we’ll work together on an acceptable installation before your qualified installer can install the generation and electrical wiring.

Final application

Submit your final application form to DGinfo.applications@vector.co.nz.

You’ll be connected on the regulated terms (Schedule 6.2) unless we ask you to sign our Distribution Generation Connection Agreement.

Connect

Connect your distributed generation system and submit all the documents outlined in the ‘responsibilities - after the installation’ section

Inspection

In some cases we’ll inspect your installation and charge a nominal fee to cover our expenses


Want to apply?


Submit the initial application form to DGinfo.applications@vector.co.nz