New simple connection

After we review your application, we’ll let you know if it is a simple connection. A simple connection only requires a quote and does not need a Vector easement. It usually takes around 6 to 8 weeks to complete. For an overview of the connections process and what to expect along the way, take a look at our Connections Journey guide here.

If you need both gas and electricity connections, please request them separately here


Please be aware of holiday period scheduling: New connections work submitted from 16 October 2026 is likely to be scheduled in the new year. See our Christmas and New Year shutdown information and service cut-off dates here.

Holiday period scheduling information


Apply for a simple connection

Please fill out the below application to start the connection process

Start application

Pricing

When you add a new connection or upgrade an existing connection on the electricity network, you will pay:

  • An assessment fee – this covers the administration costs of assessing your application and preparing your connection quote.
  • The cost of the lowest-cost connection design – this covers the work needed to connect your property or upgrade your existing connection, based on the lowest-cost design that meets Vector’s network standards.
  • Any customer-selected enhancements – these are optional enhancements you request above the lowest-cost design and will be shown separately in your quote. For example, this could include requesting a power pole to be removed.  


Connection Fee

Development contribution

Assessment fee

Total

Pricing effective from 1 April 2026 (Incl. GST)

Priced per job

See table below

$300

Priced per job


Development contribution


Network Tier

Connection type

Amount

($ per ICP)

Rate

($ per installed kVA)

Pricing effective from 1 April 2026 (Incl. GST)

Low voltage mains


Residential 0 - 14kVA

Residential 15 - 69kVA

SME 14 - 28kVA

SME 29 - 42kVA

SME 43 - 69kVA

Other low voltage mains

$3,193

$5,339

$3,703

$7,478

$15,274







$264.50

Distribution substation


Priced per job

High voltage feeder


Priced per job

Zone substation


Priced per job

Sub-transmission line


Priced per job


Civil work and traffic management

New electricity connections may require civil work and/or traffic management. You have the option to organise this yourself, using appropriately qualified providers who can meet the relevant standards and requirements. Alternatively, we can arrange it for you through our service providers. We are happy to talk through the options with you during the assessment of your connection request. 

For some complex works that involve critical network infrastructure, we may need to use our specialist contractors to complete parts of the civil work. This ensures the safety and integrity of the network. Where this applies, you cannot, unfortunately, organise those specific aspects independently. If this is the case, we will let you know during the connection process. 

If you choose to organise your own civil works, Vector will need to carry out quality assurance inspections to ensure those works meet the necessary safety and network requirements. A fee applies for this inspection process, which we’ll discuss and confirm with you as part of your connection costs.


Assessment fee

Before we can provide you with a formal quote, we need to assess your connection application. There is an upfront, non-refundable assessment fee of $300 for this work.  You can request an alternative quote if you would like to explore another connection option. A separate assessment fee applies for each quote you request.


Refunds

Sometimes the work may cost less than we originally quoted,  for example if fewer traffic management days are needed.  If this happens, we’ll refund you the difference once the work is complete.


How development contributions relate to network capacity

When you connect to the network or upgrade your connection, you use some of the network’s available capacity.

The network capacity cost is the estimated cost of providing the shared network capacity used or added to support your connection. Your development contribution is the amount you are asked to contribute towards this cost and may be less than the full network capacity cost.

Our approach is that customers creating growth on the network should contribute towards the investment needed to support that growth. How these costs are shared is subject to electricity industry regulation.

For more information about development contributions, network capacity costs and how these are changing, see our FAQs below.


Network Tier

Posted capacity rates ($ excl. GST per diversified kVA)

For information purposes only

Nominal incremental capacity (installed kVA)


1st April 2026

1st April 2027

1st April 2028

1st April 2029

1st April 2030


Low voltage mains

-

-

-

-

-

-

Distribution substation

$176.67

$180.62

$185.12

$189.95

$195.02

687,891

High voltage feeder

$715.89

$731.92

$750.15

$769.72

$790.28

321,650

Zone substation

$330.38

$337.78

$346.19

$355.22

$364.71

1,427,250

Sub-transmission line

$370.74

$379.05

$388.49

$398.62

$409.27

625,250


Pioneer schemes

A pioneer scheme helps make sure the cost of new electricity infrastructure is shared fairly.

If you’re the first customer to pay for a qualifying network extension, you may receive a refund if other customers later connect to and use that same infrastructure in the future.

Likewise, if you connect later and benefit from infrastructure someone else helped fund, you may need to contribute to these costs.

If a pioneer scheme is relevant to your connection, we will explain this clearly as part of your quote.

The table below shows the pioneer schemes that are currently active:


Pioneer reference

Location

Start date

End Date

Opening value ($)

There is currently no active Pioneer scheme in place


Our process

The process and timeframes may vary depending on a number of factors, including:

  • Whether an existing network connection supply point is available
  • The type of network connection supply point required, which depends on the available capacity
  • The number of connections you require and whether these are temporary or permanent
  • The available capacity as well as fuse and phase requirements (your electrician will provide these details)
  • The size of the current job queue for new connections
  • The conditions of the work site and the complexity of the job 
  • When traffic management services are next available (as these are managed by third parties) and the availability of equipment required 
  • Other technical, legal, regulatory and administrative factors (including resource constraints)


Initiate

Request a new connection here or ring our call centre on 0508 832 867

Design

We will review your application and contact you if further information is required. Pay the assessment fee online within 20 working days

Quote and payment

You will usually be supplied with a quote including terms and conditions within 7 working days. Pay the quote online with a credit card or through a bank transfer within 35 working days before the quote expires.

Build and variations

Connection is generally completed 40 working days after payment has been received. Final reinstatement is usually completed within 10 working days after the new connection is supplied.

Completion

When you are ready to liven your connection click here. For subdivisions, we will email you a Certificate of Completion, which you can forward to Auckland Council to apply for a 224C subdivision certificate.

Please be aware of holiday period scheduling: New connections work submitted from 16 October 2026 is likely to be scheduled in the new year. See our Christmas and New Year shutdown information and service cut-off dates here.