New simple connection
Once we have assessed your new connection application, the connection process will be described as a ‘simple connection supply point’ if it only requires a quote, but not an easement, and can usually be completed in approximately 6-8 weeks.
If you need both gas and electricity connections, please request them separately here.
Apply for a simple connection
Please fill out the below application to start the connection process
Start applicationExplore this page:
Pricing
When you add a new connection or upgrade an existing connection on the electricity network, you will pay:
- The cost of the connection at the point of supply (connection fee);
- Contribution towards costs of increasing capacity in the shared network (development contribution); and
- The cost we incur when preparing a detailed quote (assessment fee).
Connection Fee | Development contribution | Assessment fee | Total |
|---|---|---|---|
Pricing effective from 1 April 2026 (Incl. GST) | |||
Priced per job | See table below | $300 | Priced per job |
Development contribution
Network Tier | Connection type | Amount ($ per ICP) | Rate ($ per installed kVA) |
|---|---|---|---|
Pricing effective from 1 April 2026 (Incl. GST) | |||
Low voltage mains | Residential 0 - 14kVA Residential 15 - 69kVA SME 14 - 28kVA SME 29 - 42kVA SME 43 - 69kVA Other low voltage mains | $3,192 $5,338 $3,703 $7,478 $15,274 | $264.50 |
Distribution substation | Priced per job | ||
High voltage feeder | Priced per job | ||
Zone substation | Priced per job | ||
Sub-transmission line | Priced per job | ||
Civil work and traffic management
New electricity connections may require civil work and/or traffic management. You have the option to organise this yourself, using appropriately qualified providers who can meet the relevant standards and requirements. Alternatively, we can arrange it for you through our service providers. We are happy to talk through the options with you during the assessment of your connection request.
For some complex works that involve critical network infrastructure, we may need to use our specialist contractors to complete parts of the civil work. This ensures the safety and integrity of the network. Where this applies, you cannot, unfortunately, organise those specific aspects independently. If this is the case, we will let you know during the connection process.
If you choose to organise your own civil works, Vector will need to carry out quality assurance inspections to ensure those works meet the necessary safety and network requirements. A fee applies for this inspection process, which we’ll discuss and confirm with you as part of your connection costs.
Refunds
Sometimes we complete work faster than anticipated, for example, less traffic management days are needed. This may result in a partial refund of the contribution that you paid. Ordinarily we’ll process any refunds after the completion of the work when we know what work was (and was not) required.
Network capacity charges:
Vector charges capacity costs to connection applicants. The rates in the table below are for information purposes only and reflect the cost of capacity determined in accordance with new regulations set by the Electricity Authority, using the best information available at the time of preparation.
For the period 1 April 2026 to 31 March 2027, we will be charging for capacity costs on the basis set out in the table above (development contribution), which is broadly in line with our historical development contribution approach.
We are required to charge capacity costs from 1 April 2027 in accordance with new regulations set by the Electricity Authority. Between 1 April 2026 to 31 March 2027, we will test the rates and the information used to prepare those rates in the table below and on completion of that testing make any necessary adjustments. Therefore, the actual rates that will be used for charging capacity from 1 April 2027 will be published in due course.
For the avoidance of doubt the rates in the table below are for information purposes only and the rates we will use for capacity charging are yet to be determined. The nominal capacity increment is the estimated added capacity used to derive the posted capacity rates.
Network Tier | Posted capacity rates ($ incl. GST per diversified kVA) For information purposes only | Nominal incremental capacity (installed kVA) | ||||
|---|---|---|---|---|---|---|
1st April 2026 | 1st April 2027 | 1st April 2028 | 1st April 2029 | 1st April 2030 | ||
Low voltage mains | - | - | - | - | - | - |
Distribution substation | $176.67 | $180.62 | $185.12 | $189.95 | $195.02 | 687,891 |
High voltage feeder | $715.89 | $731.92 | $750.15 | $769.72 | $790.28 | 321,650 |
Zone substation | $330.38 | $337.78 | $346.19 | $355.22 | $364.71 | 1,427,250 |
Sub-transmission line | $370.74 | $379.05 | $388.49 | $398.62 | $409.27 | 625,250 |
Active pioneer schemes
A pioneer scheme is a refund mechanism that electricity distributors are required to set up from 1 April 2026 so that the customer who initially funds a qualifying network extension can be reimbursed by later customers who connect to and use that same extension.
This means that initial connections may receive refunds if others connect later and subsequent connections may be charged to contribute to earlier shared infrastructure.
If a pioneer scheme is relevant to your connection, we will explain this clearly as part of your quote.
The table below shows details of the current active pioneer schemes:
Pioneer reference | Location | Start date | End Date | Opening value ($) |
|---|---|---|---|---|
There is currently no active Pioneer scheme in place | ||||
Our process
The process and timeframes may vary depending on a number of factors, including:
- Whether an existing network connection supply point is available
- The type of network connection supply point required, which depends on the available capacity
- The number of connections you require and whether these are temporary or permanent
- The available capacity as well as fuse and phase requirements (your electrician will provide these details)
- The size of the current job queue for new connections
- The conditions of the work site and the complexity of the job
- When traffic management services are next available (as these are managed by third parties) and the availability of equipment required
- Other technical, legal, regulatory and administrative factors (including resource constraints)
Initiate | Request a new connection here or ring our call centre on 0508 832 867 |
|---|---|
Design | We will review your application and contact you if further information is required. Pay the assessment fee online within 20 working days |
Quote and payment | You will usually be supplied with a quote including terms and conditions within 7 working days. Pay the quote online with a credit card or through a bank transfer within 35 working days before the quote expires. |
Build and variations | Connection is generally completed 40 working days after payment has been received. Final reinstatement is usually completed within 10 working days after the new connection is supplied. |
Completion | When you are ready to liven your connection click here. For subdivisions, we will email you a Certificate of Completion, which you can forward to Auckland Council to apply for a 224C subdivision certificate. |
FAQs
We'll send you a tax invoice for the price once payment has been received.
If a quote is not paid within 55 working days, we'll close your application. If you'd like to proceed with the work after the quote has expired, please apply for a new connection and we will re-issue another quote. This is because material prices or site conditions may have changed since the original quote was issued.
If your job requirements change, we will supply a new design and corresponding quote.
There are several factors, including:
- The number of jobs currently in our queue
- We are reliant on third parties for traffic management and equipment supply
If that happens, we'll evaluate the impact on costs and timeframes and confirm whether there are any price adjustments. In the event there are price adjustments, we'll provide you with an updated quotation. If there's additional costs as a result of a change in requirements, all work will stop until you have agreed to and paid for the additional costs.
Our network equipment is generally installed on the corner boundary of a property by the driveway, in accordance with our network design standards. However, we are happy to discuss any specific requests you may have and will try to accommodate where possible.
Your electricity retailer owns the meter and is responsible for it, please discuss the meter position and clearance requirements with them.
If you’ve accepted the quote and Vector has had to do work on your behalf, i.e. begun digging a trench, and you then decide to cancel, you’ll be refunded less reasonable costs incurred.
Please apply as soon as you can, as this allows us more time to get ready to connect you. We encourage you to discuss your electricity connection requirements with a registered electrician prior to requesting a new connection.
If you hit a fibre cable, please call us immediately on 0800 826 436 (select option 1, then select option 2 for Vector Fibre).