How Auckland pays for a growing electricity network

25 November 2026

Vector connections nz explainer

 Auckland keeps growing and our electricity network is growing with it. New homes and businesses are connecting, while electric vehicles, data centres and businesses switching from fossil fuels are all increasing demand for electricity.

 Our principle is simple: growth should pay for growth. New developments contribute to the extra network capacity they need, rather than those costs being recovered more broadly from all electricity customers.

 Connection charges can be complicated, though, so here are answers to five of the questions we hear most often.

 

1. What do connection charges cover?

There are two parts. The connection fee pays for the work needed to connect a home, development or business. The development contribution goes towards shared capacity needed for growth, such as cables, transformers and substations.

2. Am I paying for the same thing twice?

No. Your upfront payment covers connecting you and a contribution towards the extra network capacity needed for growth. Your ongoing line charges pay for operating, maintaining and renewing the wider network you use every day.

Importantly, Vector cannot earn a return through ongoing line charges on infrastructure that customers have already paid for upfront.

3. Why do new connections contribute to network growth?

Before 2021, more of the cost of growth was recovered from electricity customers more broadly through lines charges. We introduced the development contribution so new connections contributed more directly towards the extra capacity they needed.

The cost did not suddenly appear in 2021 - what changed was how more of that cost was allocated.

4. Why can Auckland cost more than other places?

Connection prices between electricity networks are not always directly comparable. Networks can recover the costs of growth in different ways, with a different balance between how much is charged upfront for a new connection and how much is recovered from customers over time through lines charges.

There can also be additional costs involved in doing connection work in Auckland. A busy Auckland street may involve traffic management, working around existing underground services and tighter road-corridor rules.

We use the lowest-cost option that safely meets the customer’s needs, and customers can arrange their own civil works and traffic management where appropriate.

5. Does Vector profit from connection work?

We do not add a profit margin to the connection work. Connection fees recover the cost of the work, including costs passed on by the service providers carrying it out. Development contributions help fund the additional network investment needed for growth.

Higher connection costs do not mean higher profits for Vector.

We know these costs matter

Connection costs can have a real impact on a project. That is why we are improving quote detail, giving customers more choice over civil works and traffic management, and continuing to look for practical ways to reduce costs and make connecting easier.

If you are thinking about getting a connection, you can find more detailed information here:
https://vector.co.nz/our-services/electricity/new-electricity-connection